After an evaluation, GNOME has moved from Bugzilla to GitLab. Learn more about GitLab.
No new issues can be reported in GNOME Bugzilla anymore.
To report an issue in a GNOME project, go to GNOME GitLab.
Do not go to GNOME Gitlab for: Bluefish, Doxygen, GnuCash, GStreamer, java-gnome, LDTP, NetworkManager, Tomboy.
Bug 661364 - Cost and duration are calculated wrong for material resources
Cost and duration are calculated wrong for material resources
Status: RESOLVED DUPLICATE of bug 306979
Product: planner
Classification: Other
Component: General
0.14.x
Other Linux
: Normal major
: ---
Assigned To: planner-maint
planner-maint
Depends on:
Blocks:
 
 
Reported: 2011-10-10 09:47 UTC by Gerald Senarclens de Grancy
Modified: 2011-10-10 09:49 UTC
See Also:
GNOME target: ---
GNOME version: ---



Description Gerald Senarclens de Grancy 2011-10-10 09:47:30 UTC
When creating a simple task (duration 1h) and assigning a worker that costs 100 per hour, the total cost is 100. When assigning additionally required material at cost 10 per piece, the required time drops to 30 minutes and the cost to 55 as if the material was a worker.

- reproduce
create two resources, one material (cost 10), one worker (cost 100)
create a task w/ 1h work and assign the two resources to it (100 percent)

- expected result
the duration of the task is 1h, the cost 110

- actual result
the duration is 30 min, the cost 55

- note
I used planner 0.14.4 on Kubuntu 11.10
Comment 1 Alexandre Franke 2011-10-10 09:49:47 UTC

*** This bug has been marked as a duplicate of bug 306979 ***