GNOME Bugzilla – Bug 138437
Slack not calculated correctly when linking to summary tasks
Last modified: 2004-12-22 21:47:04 UTC
If a summary taks is used as a predecessor, then the subtasks of the predecessor task calculate a slack as if they were not depended upon for the subsequent tasks.
Created attachment 26073 [details] planner file example of incorrect slack calculation As you can see in the Gantt view, t2 is dependent on t1. In the Task view, t1.1 and t1.2 both show 2 days of slack, when they should both have zero slack.
This is the same bug as #137063, see http://bugzilla.gnome.org/show_bug.cgi?id=137063 That one has been fixed, but AFAIK the patch is not yet in CVS.
Fixed in CVS.