After an evaluation, GNOME has moved from Bugzilla to GitLab. Learn more about GitLab.
No new issues can be reported in GNOME Bugzilla anymore.
To report an issue in a GNOME project, go to GNOME GitLab.
Do not go to GNOME Gitlab for: Bluefish, Doxygen, GnuCash, GStreamer, java-gnome, LDTP, NetworkManager, Tomboy.
Bug 135578 - Resource unit allocation not changable
Resource unit allocation not changable
Status: RESOLVED OBSOLETE
Product: planner
Classification: Other
Component: Resources
unspecified
Other Linux
: Normal enhancement
: ---
Assigned To: planner-maint
planner-maint
Depends on:
Blocks:
 
 
Reported: 2004-02-27 09:58 UTC by Patrick Demaerschalk
Modified: 2021-06-09 20:28 UTC
See Also:
GNOME target: ---
GNOME version: Unversioned Enhancement



Description Patrick Demaerschalk 2004-02-27 09:58:40 UTC
When assigning more than one resource to a tast the unit allocation
defaults to the same percentage for each resource. E.g. if the total work
is 140 % and you assign two resources both default to 70 units. It would be
a great enhancement if it becomes possible to assign units to each resource
separately. E.g. in the previous example resource A 100 units and resource
B 40 units. Thanks.
Comment 1 Lincoln Phipps 2004-07-24 16:57:48 UTC
This is for fixed duration tasks. I'm confident that we could easily allow the
units to be adjusted manually and when the user applies the changes then
untweaked resources get forced to the correct unit allocation.

Consider the example. If the work need 140 units to complete e.g. 14 days work
in 10 days duration and they have two resources then each by default would
normally go to a 70:70 split but if you did want a 40:100 split then set
Resource A (as suggested to 40) and hit a (now and as yet undefined) apply
button. Planner would adjust any unchanged resource to meet the required units.

Just my thoughts at this time. I also need something like this to tweak resource
allocations to stay below a predefined maximum units for a resource (automatic
scheduling ideas).

Comment 2 Lincoln Phipps 2004-07-24 17:03:51 UTC
...the idea is that you adjust each resource in turn and Planner adjust the
remaining unadjusted resources. If your tweaks results in any a subsequent
recalculation and causes any resource to go over its maximum (when we eventually
define this) then your last change is undone.

So if you have 3 resources and had 180 units to do (18 days work for 10 days
duration) and wanted a 100, 50, 30 then the flow is,

Starting point (default) => r60, r60, r60
Adjust resource A to 100 => 100, r40, r40
Adjust resource B to 50  => 100, 50, r30

where r'x' means remainder.
Comment 3 GNOME Infrastructure Team 2021-06-09 20:28:54 UTC
-- GitLab Migration Automatic Message --

This bug has been migrated to GNOME's GitLab instance and has been closed from further activity.

You can subscribe and participate further through the new bug through this link to our GitLab instance: https://gitlab.gnome.org/World/planner/-/issues/38.