GNOME Bugzilla – Bug 165948
Wrong report when work day <> 8 hours
Last modified: 2008-01-19 21:02:44 UTC
First, set up a working day of 7.5 hours. Whenever I try to create a task taking 10 days (for example), I end up with a 10d 5h task. If I switch to Gantt Chart and try to modify the work (double-click/Enter in the 'Work' field), but don't modify and press 'Enter' again, the field would "grow". Subsequent 'enter's would only increase this value. Also, in the exported HTML file, the 10 days task (which appeared in the Gantt Chart as having 10 days and 5 hours) is only taking 9d 3h. NOTE: The 7.5 hours work day is not unusual. I work for a canadian company that has a work day of 7.5 hours. I also worked before for a french company. They also had a reduced work day. When I left the french company, their government was thinking about having a 7.25 hours work day!! :) I can't just use an 8 hours work day. Each month we generate a report saying how many hours we spent on each project. Planner seems to take the 8h work day for granted! But it's not...
I noticed this same bug and it makes the use of Planner for me impossible. If anyone wants an example of project that shows this bug, I can send mine.
I have been unable to reproduce this in any version from 0.13 onwards. If the problem still exists, please reopen this bug.